Resolution awarding Bid No. 0317-1980 to 4 C’s Trucking and Excavation, Inc., 331 Sawgrass Road, Bunnell, FL 32770 in the amount of $3,427,399.71 and declaring S.E. Cline Construction, Inc. a non-responsive bid. The purpose of the project is to construct the Bennett Swamp Wetland Rehydration distribution system to dispose of reuse water and lower discharges to the Halifax River.
The project will be fully funded by the following amounts upon the adoption of the FY 2017/2018 budget:
-
$1,131,041.91 (SJRWMD Cost Share Grant - 33%)
-
$1,713,699.86 (FDEP LP 64095 Grant- 50%))
-
$582,657.94 (Renewal and Replacement 8% Fund - 17%)
Recommendation: Business Enterprise Management Director recommends adoption of the Resolution.