Item as displayed on the Agenda:
| Resolution approving a final reconciliation agreement for the Beach Street Backflow Preventers, Contract 0316-2040 with Gregori Construction, Inc., 3950 South St., Titusville, FL 32780 with the following stipulations:
-
Approve March 6, 2017 as the substantial completion date for Beach Street Backflow Preventers, contract 0316-2040
- Approve June 6, 2017 as the final completion date for Beach Street Backflow Preventers, contract 0316-2040
- Approve $15,871.96 as full compensation for the balance of contract 0316-2040 including the final pay request and retainage
-
Approve the final adjusted contract price of $292,165.00 for Beach Street Backflow Preventers, contract 0316-2040
-
Approve a contact extension of 67 contact days due to event conflicts in Riverfront Park
Recommendation: Business Enterprise Management Director recommends adoption of the Resolution. |
|